Santai Rubber Industry organizes emergency drills for liquefied gas leakage accidents

01.jpg

June 2024 is the 23rd "Safety Production Month" nationwide, aimed at deepening the study of General Secretary Xi Jinping's important statements and instructions on safety production, promoting the implementation of safety production responsibilities, and strengthening citizens' safety awareness. On the afternoon of June 24th, Santai Rubber Industry organized an emergency drill for liquefied gas leakage accidents in the first phase of the factory area.

Practice simulation scenario

During the unloading process of propane, the operator was monitoring the liquefied gas tank area. At this moment, the metal hose at the front end of the unloading pump suddenly burst, and a large amount of propane sprayed out and quickly spread to the surrounding areas. The white smoke billowed on the scene, and the operator fainted due to acute inhalation of the splashed liquefied gas. The driver promptly pulled up the emergency shut-off valve behind the tanker and quickly evacuated.

Using this as a drill scenario, conduct a comprehensive emergency rescue plan drill.

1. Propane leakage

02.jpg

When the operator was monitoring the liquefied gas tank area, the metal hose at the front end of the unloading pump suddenly burst, and propane sprayed and spread outwards. The operator fainted due to acute inhalation of liquefied gas, and the driver immediately cut off the valve and quickly evacuated.

03.jpg

2. The on-site combustible gas leakage alarm reports a high alarm, and the unloading pump and delivery pump are interlocked to stop. The root shut-off valves of the liquefied gas storage tank are all interlocked and closed; However, the residual liquefied gas in the propane unloading pipeline is still leaking.

2. The central control room receives an alarm signal

04.jpg

The combustible gas leakage alarm system and DCS control system in the central control room simultaneously issued an alarm. The on duty personnel checked the alarm information and watched the video surveillance footage, and found a large amount of white smoke at the unloading site. They quickly reported to the safety director.

05.jpg

After reviewing the accident information in the control room, the safety director immediately reported the propane leakage accident to the company's general manager and activated the comprehensive emergency plan as required.

3. Activate the comprehensive emergency plan

06.jpg

The general manager and executive vice president received the alarm at the same time

07.jpg

The general manager schedules and directs on-site emergency rescue work through a video surveillance system in the control room

4. The grout workshop reported an alarm and personnel were evacuated

08.jpg

The sealant workshop alarm emits sound and light alarms

09.jpg

Organize personnel evacuation

5. Each emergency team carries out rescue operations separately
10.jpg

 

11.jpg

Members of the emergency repair team enter the scene of the accident

12.jpg

(1) The members of the emergency repair team lifted the suffocated and unconscious employee to a safe area and handed it over to the on-site rescue team for first aid.

(2) The rescue team members carry first aid kits and oxygen respirators and are on standby on the east side of the tank area. After rescuing the injured, they will immediately receive emergency treatment and oxygen therapy, and then be sent to the hospital.

6. Emergency rescue and repair at the scene of the accident

13.jpg

14.jpg

The concentration of combustible gases in the on-site air decreased to below 4% LEL, and the pipeline valves were further manually closed. The accident was effectively controlled, and the emergency repair team arranged for maintenance personnel to immediately replace the damaged steel wire hoses.

7. The accident was effectively handled and the response was terminated  

15.jpg

The wastewater generated by on-site dilution and washing is directed to the accident pool, and a dedicated person is arranged to test the hazardous substance data of the wastewater. After meeting the standards, it is disposed of according to the wastewater disposal procedures.

8. Summary of emergency drills

16.jpg

After the drill activity, the general manager commented on the emergency drill plan for liquefied gas leakage, pointed out the shortcomings, and proposed improvement suggestions.

The emergency drill effectively improved the emergency response capabilities of employees, company emergency rescue agencies, and teams in the event of hazardous chemical leakage accidents. Enhanced the overall emergency response capability of employees and the emergency awareness of all staff. Enable employees to further understand what may happen after a leakage accident, while inspecting the performance and technical condition of fire-fighting facilities.

上一篇:Apology Letter

下一篇:Return to List